Is your server room really "sealed"?
Data centers are the digital heart of enterprises. To protect expensive IT equipment, clean gas fire suppression systems such as heptafluoropropane, IG541, etc. have become standard.
However, a fatal issue that most owners overlook is this: after the extinguishing gas is discharged, if the enclosure cannot maintain sufficient airtightness, the extinguishing agent will dissipate within minutes — and the fire will re-ignite.
In server rooms dense with cable trays and numerous wall-penetrating pipes, "leakage" and "fire compartmentation failure" are the most concealed and most dangerous safety blind spots of data centers.
Many owners purchase FM/UL-certified firestop putty and fire-resistant boards and assume "all is well."
The reality is otherwise: the effectiveness of firestopping depends on a complete closed loop of "Design → Installation → Inspection → Maintenance" (DIIM). Any small human deviation in the installation phase — incorrect annular clearance, insufficient fill depth — can render an entire fire barrier ineffective during a fire. You can buy compliant materials, but you can't buy a compliant system.
To thoroughly solve the industry's chronic problem of "someone performs the work, no one takes responsibility," Shanghai Tengxi (TKC) launched a four-step closed-loop delivery solution: "Testing → Diagnosis → Repair → Verification":
Step2|Airtightness Testing and Problem Diagnosis
As one of the very few firestop contractors in Asia certified to FM 4991, TKC comprehensively rectifies every detected defect:
Choosing an FM-certified contractor is essentially purchasing a quality assurance system endorsed by an international third party. Don't let the safety of your data center be ruined by an inconspicuous gap.
TKC — Science-based Industrial Safety & Protection
For more technical details or a professional assessment, please contact the TKC expert team.